POWER PROJECTS

New and Ongoing Power Projects :

1. Projects under Implementation:

Project

Capacity  (MW)

Annual Energy in MU

Project Cost  Rs.Cr

Expected

Completion

Yeramarus TPP Unit-2

1600

11913

9015

August-16  

TOTAL

1600

11913

9015

 


2. New Power Projects

New Project

Capacity  (MW)

Annual Energy  in MU

Cost  Rs.Cr

Expected Completion

Godhna TPP, Chhattisgarh

1600

11914

11333

Unit-1 :48 months from LoA
Unit-2 :54 months from LoA

Edlapur TPP

800

5957

4960

51 months from LoA

Bidadi CCPP

700

2500

2500

Under Litigation

Munirabad

10

11

44

June-2016

Ghataprabha

20

40

99

-

Gundia

400

1002

1333

-

Shivasamudram

345

1290

750

 

Tadadi CCPP

2100

15637

7350

-

Yelahanka CCC Plant

350

-

1571

LOI issued to BHEL, GTA requires to be signed with GAIL 

TOTAL

6325

38351

29940

 


3. Long Term Plan (PCKL as a Nodal Agency):

Sl. No.

Project Name

Capacity

CASE-2 BID ROUTE

1

Gulbarga Thermal Power Project

1320 MW (2X660)

2

3 No.s of  700MW Gas Based Power Projects each  in the districts of Belgavi, Gadag and Davanagere

2100 MW (3X700)

MOU ROUTE – Central Government

1

Kudgi Super Thermal Power Project

4000 MW

2

KAIGA Nuclear Power Plant

(unit 5 & 6 enhancement  to 700MW)

1400 MW

3

Greenfield Nuclear power plant at Mannur, Bijapur Dist

2100MW (3X700)

MOU ROUTE – IPPs

1

Hassan Thermal Power Pvt. Ltd

500 MW


4. List of New Projects scheduled for 12 & 13th Plan for Capacity Addition (under long term)

   

Year

Projects

Utility

% Allocation

State Share (MW)

Sector

2015-16

BTPS Unit-3 (700 MW)

KPCL

100%

700

State

Yermarus (1X800MW) Unit-1

KPCL

100%

800

State

Yermarus (1X800MW) Unit-2

KPCL

100%

800

State

Kudamkulam Unit- 2 (1*1000MW)

NPCIL

22%

221

CGS

Total Capacity addition Commissioned in 2015-16

2521


2016-17

Kalpakam PFBR - 500 Mwe

BHAVANI

17%

85

CGS

Kudgi Unit- 1 (1X800 MW)

NTPC

50%

400

CGS

Kudgi Uni-2 (1X800 MW)

NTPC

50%

400

CGS

DVC

PCKL

 

450

CGS

Total Capacity addition by 2016-17

1335


2017-18

Kudgi Unit- 3 (1X800 MW)

NTPC

50%

400

CGS

NLC New TPP-U#1 (1X500)

NLC

7%

35

CGS

Yelahanka Gas based Power Plant  (1X350 MW) Phase -I

KPCL

100%

350

State

Total Capacity addition by 2017-18

785


2018-19

Bidadi -Gas- (700 MW)

KPCL

100%

700

State

NLC New TPP U#2 (1X500)

NLC

7%

35

CGS

Total Capacity addition Commissioned in 2018-19

735


2019-20

Edlapur-800MW*

KPCL

100%

800

State

Cheyyur UMPP U-1 (1X800 MW)

UMPP

20%

160

CGS

Kaiga Expansion Unit-1(700 MW)

NPCIL

50%

350

CGS

Total Capacity addition Commissioned in 2019-20

1310


2020-21

Sirkali Power Project  Unit-1 (1X660)

NLC

20%

132

CGS

Cheyyur UMPP U-2 (1X800 MW)

UMPP

20%

160

CGS

Cheyyur UMPP U- 3 (1X800 MW)

UMPP

20%

160

CGS

Kaiga Expansion Unit-2(700 MW)

NPCIL

50%

350

CGS

Total Capacity addition Commissioned in 2020-21

802


2021-22

Sirkali Power Project Unit-3 (1X660)

NLC

20%

132

CGS

Sirkali Power Project Unit-3 (1X660)

NLC

20%

132

CGS

Cheyyur UMPP U-4 (1X800 MW)

UMPP

20%

160

CGS

Cheyyur UMPP U-5 (1X800 MW)

UMPP

20%

160

CGS

Total Capacity addition Commissioned in 2021-22

584


Capacity addition by Central generating Stations in 2017-22

2367


Capacity addition by State generating Stations in 2017-22

1850


 Total Capacity addition in 13th Plan (2017-22)

4217



Designed and Developed by: Energy Department, Government of Karnataka

Disclaimer: Please note that this page also provides links to the websites / web pages of Govt. Ministries/Departments/Organisations. The content of these websites are owned by the respective organisations and they may be contacted for any further information or suggestion.

Designed and Developed by: Center for e-Governance Government of Karnataka

©2016, All Rights Reserved.

india-gov-logo
pm india
CM Karnataka logo
nic logo
Top